Delivery of equipment

16.05.2017 · 1172

The first batch of process equipment for Hydrocracking unit was supplied:


The Orsknefteorgsintez site final assembly for columns K-02 and K-03 was completed with volume heat treatment at site.

Columns of pos. K-101, K-02, and also the separator pos. S-03 were made of clad plates of «PETROSTALPROKAT TM» Ltd.

The start-up of the hydrocracking unit is planned in 2018.

In May 2017, the first pretreatment reactor for pos. R-01 was delivered to Customer. The reactor was made of Cr-Mo-V steel with thickness of 140 mm with stainless steel cladding with a thickness of 5 mm.

At the end of this month it is planned to supply the second hydrocracking reactor pos. R-02.

At the moment this reactor was manufactured and is waiting for shipment to Customer.

The reactors are made on the basic project of the licensor.